PROPOSED SCHEDULE <br />The RMI Team is ready to deliver this project to the City of Sunny Isles and North Miami <br />Beach within 730 day. A well-executed phased construction method is crucial to best <br />delivery this project in a safe and expedited manner. <br /> <br />Our Project scheduling approach is to establish a timeline for delivering the project and <br />most importantly, the project activities and their respective inter-relationships. Avoiding <br />missing deadlines for delivery of key project components is a key objective of our <br />schedule management plan. Our detailed project schedule will identify all the project's <br />stages, phases, and activities to keep track of work progress. Our Schedule management <br />plan interfaces directly with scope, cost, and quality optimization. Our goal is to look for <br />potential issues and efficiencies in all these areas as project progress. <br /> <br />Preparing the detailed project schedule will consist of developing the Work Breakdown <br />Structure (WBS) and understanding critical project milestones, requirements and <br />constraints which impact the timing and sequencing of the work; then integrating and <br />developing this information into the project schedule. <br /> <br />Due to current supply chain issues/conditions material may take up to 4 months to deliver <br />for when the order is placed. It would be extremely difficult to provide a detailed schedule <br />prior to NTP, for this reason RMI will provide a detailed schedule within 14 days of NTP. <br />These activities shall be of sufficient detail to ensure an appropriate basis for monitoring <br />and evaluating the sequence of the work and shall include major constraints including <br />long-lead items. <br /> <br />Project schedules are to be monitored and updated weekly to determine those critical <br />milestones are being met and those activities are progressing as required. Updating the <br />schedule consists of the following three (3) basic steps: <br />• Status of the actual progress and forecast to complete <br />• Incorporation of new information, which may require adjusting the schedule <br />logic and durations <br />• Analyses of variation(s) to the target schedule <br /> <br />The Critical Path will be determined by those activities with the least amount of total float. <br />Critical path activities control the overall duration of the project. An activity with less than <br />10 days total float is critical and will require monitoring on a regular basis to ensure timely <br />completion of the project.