<br />THE CITY OF SUNNY ISLES BEACH <br />PROJECT NO. 21-1011 <br />BUILDING DEPARTMENT RELOCATION TO ANNEX <br /> <br /> <br />Project No. 21-1011 November 2024 019113 Commisioning General <br />Requirements-1 <br /> <br />SECTION 019113 <br />COMMISSIONING GENERAL REQUIREMENTS <br /> <br />PART 1 – GENERAL <br /> <br />1.1 RELATED DOCUMENTS <br /> <br />A. Drawings and general provisions of the Contract, including General and <br />Supplementary Conditions and other Division 01 Specification Sections, apply to this <br />Section. <br /> <br />B. OPR and BOD documentation are included by reference for information only. <br /> <br />1.2 SUMMARY <br /> <br />A. Section includes general requirements that apply to implementation of <br />commissioning without regard to specific systems, assemblies, or components. <br /> <br />1.3 DEFINITIONS <br /> <br />A. BOD: Basis of Design: A document that records concepts, calculations, decisions, <br />and product selections used to meet the OPR and to satisfy applicable regulatory <br />requirements, standards, and guidelines. The document includes both narrative <br />descriptions and lists of individual items that support the design process. <br /> <br />B. Commissioning Agent (CxA): Owner compensated independent agent, not otherwise <br />associated with the Commissioning team members or the Contractor. The CxA <br />directs and coordinates the day-to-day commissioning activities. <br /> <br />C. Cx: Commissioning. <br /> <br />D. Commissioning Plan: Overall plan that provides the structure, schedule and <br />coordination planning for the commissioning process. <br /> <br />E. Functional Performance Test: Test of the function and operation of equipment and <br />systems. Functional testing is the dynamic and interactive testing of systems under <br />full operation. Systems are tested under various modes, such as during low cooling <br />or heating loads, high loads, component failures, unoccupied, varying outside air <br />temperatures, power failure, etc. The systems are run through all the control <br />system's sequences of operation and components are verified to be responding as <br />the sequences state. The commissioning agent develops the functional test <br />procedures in a sequential written form, coordinates, oversees and documents the <br />actual testing, which is performed by the installing contractor or vendor. Functional <br />tests are performed after pre-functional checklists and start-up are complete. <br />Functional Performance Testing is not traditional air or water test and balancing. <br /> <br />F. Pre-functional Checklist: A list of items to inspect and elementary component tests <br />to conduct to verify proper installation of equipment, provided by the CxA to the <br />Contractor. Pre-functional checklists are primarily static inspections and procedures <br />to prepare the equipment or system for initial operation. Some pre-functional <br />checklist items entail simple testing of the function of a component, a piece of