2. QUALIFICATIONS
<br />43SRS Engineering, Inc.• RFQ No. 26-07-01
<br />2. QUALIFICATIONS _______________
<br /> Corrosion and material life. Salt air and brackish groundwater shorten the life of standard materials.
<br />Specification choices for structures, hardware, coatings and pipe materials materially affect the City’s
<br />maintenance cost.
<br /> Layered permitting with long review cycles. RER/DERM, FDOT, SFWMD, FDEP and ACOE reviews are on the
<br />critical path more often than design is. Pre-application coordination is the single highest-leverage schedule
<br />control available.
<br /> Resiliency and grant funding. Federal and state resilience funding carries documentation, reporting and
<br />eligibility requirements. Getting that right at scoping avoids reimbursement problems later.
<br />PROJECT LIST — RELEVANT EXPERIENCE IN MIAMI-DADE, BROWARD AND PALM BEACH COUNTIES
<br />All projects listed below are located in Miami-Dade County, Florida. Each entry gives the owner and the owner’s
<br />representative familiar with the work
<br />PROJECT OWNER Status SRS Role Owner’s
<br />Representative
<br />Cutler Ridge Pines Drainage and
<br />Roadway Improvements ($2.5M ARPA,
<br />approx. 6,295 LF) — APWA Consultant
<br />of the Year, Stormwater
<br />Town of Cutler Bay,
<br />10720 Caribbean Blvd.,
<br />Cutler Bay, FL 33189
<br />Complete Prime; Engineer of
<br />Record and CEI
<br />Alfredo Quintero, Public
<br />Works Director, (786)
<br />573-5520
<br />Saga Bay 1.5 South Roadway and
<br />Drainage Improvements — delivered on
<br />schedule and under budget (2024)
<br />Town of Cutler Bay Complete Prime; Engineer of
<br />Record
<br />Alfredo Quintero, (786)
<br />573-5520
<br />B-50904 NW 7th Street Road Drainage
<br />Improvements, NW 9th Court to NW
<br />North River Drive — outfall to Seybold
<br />Canal, upsized conveyance, curb and
<br />gutter, sidewalk back raising, milling and
<br />resurfacing
<br />City of Miami, 444 SW
<br />2nd Avenue, Miami, FL
<br />33130
<br />Construction
<br />completed
<br />1/2025
<br />Civil Engineer of
<br />Record
<br />Juvenal Santana, Jr., P.E.,
<br />CFM, (305) 416-1200
<br />Citywide Sanitary Sewer Master Plan
<br />— 12 subarea plans, approx. $46.8M of
<br />identified improvements
<br />City of South Miami,
<br />6130 Sunset Drive,
<br />South Miami, FL 33143
<br />Complete Prime; Civil Engineer
<br />Alex Muñoz, Director
<br />of Public Works & CIP,
<br />(305) 403-2078
<br />Ojus Sanitary Sewer Improvements — 1
<br />new pump station, approx. 9,915 LF
<br />gravity sewer, 98 new laterals; part of
<br />pump station and pipeline upgrades at
<br />50+ stations
<br />Miami-Dade Water and
<br />Sewer Department
<br />Permitted and
<br />delivered for
<br />construction
<br />Prime; Civil Engineer of
<br />Record
<br />Juan Curiel, P.E., (786)
<br />552-8399
<br />NW 58th Street Reconstruction,
<br />SR-836 to NW 97th Avenue — 4-lane
<br />section with center turn lane, drainage,
<br />signalization and lighting
<br />Miami-Dade County
<br />Department of
<br />Transportation and
<br />Public Works
<br />Complete Prime; Civil Engineer of
<br />Record
<br />Fernando Mardones,
<br />(305) 375-4455
<br />NW 142nd Street Water and Sewer
<br />Improvements ($2.495M construction),
<br />permitted through DERM and Health
<br />City of Hialeah, 501
<br />Palm Avenue, Hialeah,
<br />FL 33010
<br />Completed
<br />2019
<br />Prime; Engineer of
<br />Record
<br />Jose Sanchez, Street
<br />Department Director,
<br />(305) 687-2611
<br />E 10th–12th Avenue from E 49th–
<br />52nd Street Roadway and Drainage
<br />Improvements — preliminary
<br />contamination study and conceptual
<br />drainage with DERM pre-approval
<br />before full design (2025)
<br />City of Hialeah Complete Prime; Engineer of
<br />Record
<br />Jose Sanchez, (305)
<br />687-2611
|