shoulders. Key elements of the project included retaining walls, waterlines and drainage.
<br />
<br />Querino Wash Interstate Highway & Bridge Replacement. Contract Value: $4 million
<br />This project was located on Interstate 40 near Gallup NM within the Navajo Indian reservation
<br />and consisted of construction of a new AASHTO girder bridge and bridge demolition. Work
<br />included roadway and rock excavation, 120" diameter drilled shafts, structural concrete for bridge
<br />construction and demolition of existing steel girder bridge.
<br />
<br />Phoenix-Goodyear Airport T-Hangars and Infrastructure. Contract Value: $7 million
<br />This project was located in the City of Goodyear near Phoenix and consisted of six hangar
<br />buildings with a total of 78 T-hangars, fully enclosed, including restrooms and two canopies
<br />covering 20 tie-down spaces. The project also included embankment for paved apron taxi lanes,
<br />storm water drainage piping, trench drains, sanitary sewer and water lines.
<br />
<br />2/96 - 9/97 Project Manager
<br />PCL Civil Southwest, Tempe, Arizona
<br />Agua Fria River Siphon Replacement and Centennial Wash Siphon Repair.
<br />Contract Value: $29 million
<br />The Agua Fria siphon replacement was located approximately 28 miles northwest of Phoenix, and
<br />consisted of construction of 2 miles of 252" diameter pipe, and the removal of approximately 640
<br />LF of existing siphon pipe. The Centennial Wash Siphon repair was located 70 miles west of
<br />Phoenix in La Paz County, AZ, and consisted of construction of approximately 900 LF of 240"
<br />diameter steel liner installed in existing prestressed concrete siphon pipe. Duties included
<br />management of both projects which were built concurrently.
<br />
<br />4/95 - 2/96 Project Engineer
<br />PCL Civil Southwest, Tempe, AZ
<br />North Metro Interceptor, Phase I. Contract Value: 25 million
<br />This project was located in San Diego, CA and consisted of construction of a new sewer
<br />interceptor pipeline requiring furnishing and installation of approximately 2 miles of 108" PVC
<br />lined reinforced concrete pipe, including manholes, four junction structures, four transition
<br />structures, and one conflict structure. The project also included 3000 LF of bored and jacked 108"
<br />pipe, streambed protection, live connections to existing pipelines, traffic control and treatment and
<br />disposal of large quantities of water and soil contaminated with hazardous waste. Duties included
<br />quantity takeoffs, scheduling, quality control, management of hazardous waste and client liaison.
<br />
<br />4/93 - 3/95 Project Engineer
<br />PCL Civil Southwest, Tempe, Arizona
<br />Salt River Siphon Replacement Project. Contract Value: $29 million
<br />This project was located near Phoenix, AZ and consisted of 2 miles of 252" diameter welded steel
<br />pipe. Duties included quantity takeoffs, scheduling, quality control, management and supervision
<br />of pipe coating operations, and client liaison.
<br />
<br />12/91 - 4/93 Project Engineer
<br />PCL Civil Southwest, Tempe, Arizona
<br />San Diego Water Authority Pipeline 4 Extension, San Diego, CA. Contract Value: $43 million
<br />This project included five ½ miles of 96" and 108" welded steel water pipe including numerous
<br />structures, relocation of conflicting utilities and street improvements.
<br />
<br />6/88 -11/91 Project Engineer and Project Manager
<br />JWJ Contracting, Tempe, Arizona
<br />Queen Creek Road Traffic interchange at Interstate 10, Phoenix, AZ. Contract Value: $4 million
<br />NW Outer loop, Bell Rd. - 75th Ave., Phoenix, AZ. Contract Value: $23 million
<br />NW Outer loop, Peoria Ave. - 75th Ave., Phoenix, AZ. Contract Value: $32 million
<br />
<br />4/87 - 5/88 Estimator
<br />Schuck and Sons Construction
<br />
<br />7/85 - 9/86 Superintendent
<br />Alps Building Contractors
|