SAMSON OCEANFRONT PARK <br />CITY OF SUNNY ISLES <br />TECHNICAL SPECIFICATIONS <br /> <br />CONSTRUCTION SCHEDULES 01310-2 <br /> <br /> <br />A construction progress report shall accompany each application for partial payment. Work reported complete, <br />but not readily apparent to the Engineer, must be substantiated with supporting data. <br /> <br />1.06 SUBMISSIONS <br /> <br />: <br /> A. Submit an initial progress schedule prior to pre-construction conference for discussion. Submit the final <br />construction progress schedule with (10) days after the effective date of the Notice to Proceed with <br />Contract Work. <br /> <br /> B. Submit updated Progress Schedules with each application for payment. <br /> <br /> C. Submit Construction Progress Report with Progress Schedules. <br /> <br />1.07 DISTRIBUTION <br /> <br />: <br /> A. Distribute copies of the reviewed schedules and construction progress report to: <br /> 1. Job site file. <br /> 2. Subcontractors. <br /> 3. Other concerned parties. <br /> <br /> B. Instruct recipients to report promptly to the Contractor, in writing, any problems anticipated by the <br />projections shown in the schedules. <br /> <br /> <br /> <br />END OF SECTION