• <br /> • Included in the plans are FDOT drawings titled "Signing and Pavement Markings". There <br /> are no bid items for this work. Are the quantities shown on Sheets S-3 to S-5 included in <br /> this bid? <br /> No, the FDOT Signing and Pavement Marking plans are included as reference only to aid in <br /> the restoration of existing pavement marking and signage. <br /> • Per the Measure and Payment section restoration costs are to be included in each of the <br /> pipe bid items (Items 6-92). Since these are shared trenches how is this to be divided <br /> among the various bid items included in the common trench? The configuration of pipes <br /> change as does the restoration necessary. For instance, at some locations the lateral trench <br /> will include asphalt, concrete median, curb and gutter, and concrete sidewalk where at <br /> others it is only asphalt, curb and gutter and decorative sidewalk, so each lateral pipe item <br /> will have to include restoring the worst case scenario. Can bid items be added for each of <br /> the types of restoration required for this project? <br /> No, you will need to quantify the amount of restoration needed based on the available <br /> information and divide it up among the bid items as you deem appropriate. <br /> • Per the Measure and Payment section the Contingency Allowance is to be used for the "off <br /> Collins" work for which we do not have any plans. The work included to be covered under <br /> this allowance does not include restoration only installation. How will the restoration for this <br /> work be paid? <br /> Section 00300 — Bid Forms has been revised. Pay item 94 "Contingency allowance..." has <br /> been deleted and is no longer a part of this bid. <br /> • Can the travel lane where the backbone trench is being installed remain closed during the <br /> day except at intersections and driveways? <br /> No, the City is adamant about opening all lanes of traffic during the day, 6:30am to 9:00pm. <br /> Work is only to be performed at night. <br /> • Can bid items be added to separate the FPL concrete pads? There is a big difference in <br /> cost for setting a single low style transformer pad and placing a switch cabinet chamber? <br /> Vista switch cabinets were broken out into their own pay item. Please refer to the revised <br /> Bid Form in Section 00300 included in Addendum No. 4. <br /> • The plans show locations where we are placing ducts to existing transformers. Are these <br /> ducts to be stubbed up inside the transformer? <br /> For purposes of the bid, please assume that you will stub the conduits at the surface <br /> outside and adjacent to the existing transformers. <br /> Monday. December 28, 2015 <br />