ARTICLE 2 -- PRELIMINARY MATTERS <br /> 2.1 DELIVERY OF BONDS/INSURANCE CERTIFICATES <br /> A. When the CONTRACTOR delivers the signed Agreements to the OWNER, the <br /> CONTRACTOR shall also deliver to the OWNER such Bonds and Insurance <br /> Policies and Certificates as the CONTRACTOR may be required to furnish in <br /> accordance with the Contract Documents. <br /> 2.2 COPIES OF DOCUMENTS <br /> A. The OWNER shall furnish to the CONTRACTOR the required number of copies <br /> of the Contract Documents specified in the Supplementary General Conditions. <br /> 2.3 COMMENCEMENT OF CONTRACT TIME; NOTICE TO PROCEED <br /> A. The Contract Time will start to run on the commencement date stated in the <br /> Notice to Proceed. <br /> 2.4 STARTING THE PROJECT <br /> A. The CONTRACTOR shall begin to perform the Work within 10 days after the <br /> commencement date stated in the Notice to Proceed, but no Work shall be done <br /> at the site prior to said commencement date. . <br /> 2.5 BEFORE STARTING CONSTRUCTION • <br /> A. Before undertaking each part of the Work, the CONTRACTOR shall carefully <br /> study and compare the Contract Documents and check and verify pertinent <br /> figures shown thereon and all applicable field measurements. The <br /> CONTRACTOR shall promptly report in writing to the ENGINEER OF RECORD <br /> any conflict, error, or discrepancy which the CONTRACTOR may discover and <br /> shall obtain a written interpretation or clarification from the ENGINEER OF <br /> RECORD before proceeding with any Work affected thereby. <br /> B. The CONTRACTOR shall submit to the ENGINEER OF RECORD for review <br /> those documents called for under Section 01330 - Submittals in the General <br /> Requirements. <br /> 2.6 PRECONSTRUCTION CONFERENCE <br /> A. A preconstruction conference attended by the CONTRACTOR, the ENGINEER <br /> OF RECORD and others as appropriate will be held to discuss the Work in <br /> accordance with the applicable procedures specified in the General <br /> Requirements. <br /> 2.7 FINALIZING SCHEDULES <br /> A. At least seven (7) days before the first Pre-Construction Meeting, a conference <br /> attended by the CONTRACTOR, the ENGINEER OF RECORD, and others as <br /> appropriate, the CONTRACTOR will submit the following documents, if required, <br /> 00700-4/39 <br /> V U <br />