SGC 10.3 FIELD ORDERS AND SUPPLEMENTAL INSTRUCTIONS: <br /> A. The Contract Administrator, through ENGINEER OF RECORD, shall have the right to <br /> approve and issue Field Orders setting forth written interpretations of the intent of the <br /> Contract Documents and ordering minor changes in Work execution, providing the Field <br /> Order involves no change in the Contract Price or the Contract Time. <br /> B. ENGINEER OF RECORD shall have the right to approve and issue Supplemental <br /> Instructions setting forth written orders, instructions, or interpretations concerning the <br /> Contract Documents or its performance, provided such Supplemental Instructions <br /> involve no change in the Contract Price or the Contract Time. <br /> SGC-10.4 CHANGE ORDERS: <br /> A. Changes in the quantity or character of the Work within the scope of the Project which <br /> are not properly the subject of Field Orders or Supplemental Instructions, including all <br /> changes resulting in changes in the Contract Price, or the Contract Time, shall be <br /> authorized only by Change Orders approved in advance and issued in accordance with <br /> the provisions of the Miami-Dade OWNER Procurement Code, as amended from time to <br /> time. <br /> B. CONTRACTOR shall not start work on any changes requiring an increase in the <br /> Contract Price or the Contract Time until a Change Order setting forth the adjustments is <br /> approved by the OWNER. Upon receipt of a Change Order CONTRACTOR shall <br /> promptly proceed with the work set forth within the document. <br /> C. In the event satisfactory adjustment cannot be reached for any item requiring a change <br /> in the Contract Price or Contract Time, and a Change Order has not been issued, <br /> OWNER reserves the right at its sole option to either terminate the Contract as it applies <br /> to the items in question and make such arrangements as may be deemed necessary to <br /> complete the disputed work; or submit the matter in dispute to ENGINEER OF RECORD <br /> as set forth in Paragraph 9.8 in the General Conditions hereof. During the pendency of <br /> the dispute, and upon receipt of a Change Order approved by OWNER, CONTRACTOR <br /> shall promptly proceed with the change in the Work involved and advise the ENGINEER <br /> OF RECORD and Contract Administrator in writing within seven (7) calendar days of <br /> CONTRACTOR's agreement or disagreement with the method, if any, provided in the <br /> Change Order for determining the proposed adjustment in the Contract Price or Contract <br /> Time. <br /> D. On approval of any Contract change increasing the Contract Price, CONTRACTOR shall <br /> ensure that the performance bond and payment bond are increased so that each reflects <br /> the total Contract Price as increased. <br /> E. Under circumstances determined necessary by OWNER, Change Orders may be issued <br /> unilaterally by OWNER. <br /> SGC-10.5 VALUE OF CHANGE ORDER WORK: <br /> A. The value of any work covered by a Change Order or of any claim for an increase or <br /> decrease in the Contract Price shall be determined in one of the following ways: <br /> 00800-7/13 <br />