We are requesting Commission approval on proposed Change Order 8 <br /> and Change Order 9. Change Order 8 requests a ninety-eight (98) day <br /> time extension due to a myriad of unforeseen conditions which have <br /> delayed the construction progress, including but not limited to weather <br /> conditions, modifications to existing utilities not owned by the City and <br /> the associated coordination with the respective utility owners. Change <br /> Order 9 covers more extensive asphalt work than previously proposed <br /> on the west side of North Bay Road in order to further enhance the <br /> surface flow of water to the existing drainage. Change Order 9 is a <br /> $27,713.50 drawdown on the $290,068 project contingency budget <br /> and has no monetary impact on the overall contract value. <br /> An additional twenty (20) days will be added to the contract time due to <br /> the increased scope of work. Combined, Change Order 8 and Change <br /> Order 9 request a 118-day extension to the existing contract. <br /> ADDITIONAL INFORMATION: <br /> The existing contract value of $3,579,582.28 remains unchanged. The <br /> new proposed project completion is approximately December 2016. <br /> FUNDING SOURCE: <br /> Funding has been appropriated in account No. 300-5-5410-465000- <br /> 84001 <br /> ATTACHMENTS: <br /> Description <br /> Resolution <br /> Change Order 8 <br /> Change Order 9 <br /> Item Number: 10.G. <br /> 111 <br />