Laserfiche WebLink
fi <br />06/07 01310 -1 <br />03 -4197 <br />SECTION <br />01310 <br />CONSTRUCTION SCHEDULES <br />PART 1 - <br />GENERAL <br />1.01 REQUIREMENTS INCLUDED <br />A. <br />Promptly after Award of the Contract and within ten days after the effective date <br />of the Agreement, prepare and submit to the Engineer estimated construction <br />progress schedules for the work, with sub - schedules of related activities which <br />are essential to its progress. <br />B. <br />Submit revised progress schedules on a monthly basis. <br />C. <br />No partial payments shall be approved by the Engineer until there is an approved <br />up to date construction progress schedule on hand. <br />D. <br />The Contractor shall designate an authorized representative of his firm who shall <br />be responsible for development and maintenance of the schedule and of <br />progress and payment reports. This representative of the Contractor shall have <br />direct project control and complete authority to act on behalf of the Contractor's <br />schedule. <br />t1.02 <br />RELATED REQUIREMENTS <br />A. <br />Section 01010: Summary of Work. <br />B. <br />Section 01152: Applications for Payment <br />C. <br />Section 01200: Project Meetings. <br />D. <br />Section 01340: Shop Drawings, Working Drawings and Samples. <br />1.03 FORM OF SCHEDULES <br />A. <br />Prepare schedules for submittal each month with pay request. The form of the <br />schedule is to be MicrosoftTM Project 4.1 a or approved equal. The Schedule is to <br />indicate work completed to date and additions to or deletions from the schedule. <br />1. Provide separate horizontal bar or CPM for each trade or operation within <br />each structure or item. <br />2. Horizontal time scale: In weeks from start of construction and identify the <br />first work day of each month. <br />3. Scale and spacing: To allow space for notations and future revisions. <br />4. Minimum sheet size: 24 inches x 36 inches. <br />1 <br />06/07 01310 -1 <br />03 -4197 <br />