<br />1--
<br />
<br />and licenses. CONTRACTOR shall pay all governmental
<br />charges and inspection fees necessary for the prosecution of
<br />the Work which arc applicable at the time of opening of Bids,
<br />or, if there are no Bids, on the Effective Date of the
<br />Agrecment. CONTRACTOR shall pay all charges of utility
<br />owners for conncctions to the Work, and OWNER shall pay
<br />. all charges of such utility owners for capital costs related
<br />thereto, such as plant investment fees.
<br />
<br />6.09 Laws and Regularions
<br />
<br />A, CONTRACTOR shall give all notices and comply
<br />with all Laws and Regulations applicable (0 the performance
<br />of the Work. Except where otherwise expressly required by
<br />applicable Laws and Regulations, neither OWNER nor
<br />ENGINEER shall be responsible for monitoring
<br />CONTRACTOR's compliance with any Laws or Regulations.
<br />
<br />B. If CONTRACTOR performs any Work knowing or
<br />lutving reason to know that it is contrary to Laws or
<br />Regulations. CONTRACTOR shall bear all claims, costs,
<br />losses, and damages (including but notliInited to all fees and
<br />charges of engineers. architects, attorneys, and other
<br />professionals and all court or arbitration or other dispute
<br />resolution costs) arising out of or relating to such Work;
<br />however, it shall not be CONTRACTOR's primary
<br />responsibility to make certain that the Specifications and
<br />Drawings are in accordance with Laws and Regulations, but
<br />this shall not relieve CONTRACTOR of CONTRACTOR's
<br />obligations under paragraph 3.03.
<br />
<br />C. Changes in Laws or Regulations not known at the
<br />time of opening of Bids (or, on the Effective Date of the
<br />Agreement if there were no Bids) having an effect on the cost
<br />or time of performance of the Work may be the subject of an
<br />adjustment in Contract Price or Contract Times. If OWNER
<br />and CONTRACTOR are unable to agree on entitlement to or
<br />on the amount or extent, if any, of any such adjustment, .a
<br />Claim may be made therefor as provided in paragraph 10.05.
<br />
<br />6.10 Taxes
<br />
<br />A. CONTRACTOR shall pay all sales, consumer, use,
<br />and other similar taxes required to be paid by CONTRAC.
<br />TOR in accordance with the Laws and Regulations of the
<br />place of the Project which are applicable during the
<br />performance of the Work.
<br />
<br />6 .11 Us~ of Site and Other Areas
<br />
<br />A. Limitation on Use of Sire and Other Areas
<br />
<br />1. CONTRACTOR shall confine construction
<br />equipment, the storage of materials and equipment, and
<br />the operations of workers to the Site and other areas
<br />permitted by Laws and Regulations, and shall not
<br />
<br />unreasonably encumber the Site and other areas with
<br />construction equipment or other materials or equipment.
<br />CONTRACTOR shall assume full responsibility for any
<br />damage to any such land or area, or to the o\lmer or
<br />occupant thereof. or of any adjacent land or areas
<br />resulting from the performance of the Work.
<br />
<br />2. Should any claim be made by any such owner or
<br />ouupant because of the performance of the Work,
<br />CONTRACTOR shall promptly settle with such other
<br />parry by negotiation or otherwise resolve the claim by
<br />arbitration or other dispute resolution proceeding or at
<br />Jaw,
<br />
<br />3. To the fullest extent permitted by Laws and
<br />Regulations, CONTRACTOR shall indemnify and hold
<br />harmless OWNER, ENGINEER, ENGINEER's
<br />Consultant, and the officers, directors. partners,
<br />employees. agents, and other consultants of each and any
<br />of them from and against all claims, costs, losses, and
<br />damages (including but Dot limited to all fees and charges
<br />of engineers, architects, attorneys, and other professionals
<br />and all court or arbitration or other dispute resolution
<br />costs) arising out of or relating to any claim or action,
<br />legal or equitable, brought by any such owner or occupant
<br />against OWNER, ENGINEER, or any other party
<br />indemnified hereunder to the extent caused by or based
<br />upon CONTRACTOR's performance of the Work.
<br />
<br />B. Removal of Debris During Peifonnance of lhe Work:
<br />During the progress of the Work CONTRACTOR shall keep
<br />the Site and other areas free from accumulations of waste
<br />materials, rubbish, and other debris. Removal and disposal
<br />of such waste materials, rubbish, and other debris shall con-
<br />form to applicable Laws and Regulations.
<br />
<br />C. Cleaning: Prior to Substantial.Completion of the
<br />WOIxCONTRAcroRshall..clean the Site and make it ready
<br />for utilization by OWNER. At the completion of the Work
<br />CONTRACTOR shall remove from the Site all tools,
<br />applianccs,construction equipment and machinery, and
<br />surplus materials and shall restore to original condition all
<br />property not designated for alteration by the Contract
<br />Documents.
<br />
<br />D. Loading Srrucrures: CONTRACTOR shall Dot load
<br />nor permit any part of any structure to be loaded in any
<br />manner that will endanger the structure, nor shall
<br />CONTRACTOR subject any part of the Work or adjacent
<br />property to stresses or pressures that will endanger it.
<br />
<br />6.12 Record Documetlls
<br />,.
<br />
<br />A. CONTRACTOR shall maint:!in in a safe place at the
<br />Site one record copy of all Drawings, Specifications,
<br />Addenda, Written Amendments, Change Orders, Work
<br />
<br />00700 - 22
<br />
|