Laserfiche WebLink
<br />06/08 <br /> <br />e) Item #74 copper clad ground rods? How long what diameter? <br />Response: 5/6" x 10' long. <br />f) I need to know the new estimated cost for this project because according <br />to Addendum NO.3 the new estimated cost is $1,345,000.00 and before it <br />was $3,450,000.00. <br />Response: The estimated cost for this project is $3,450,000.00. <br />g) I need to know if you already have a new estimated cost for the alternate <br />bid "Atlantic Isles System Betterment" in North Miami Beach. <br />Response: The Bid Tab will contain bid items for the North Miami <br />Beach Water Distribution System. <br />h) I also need to know if the alternate project will need a bid bond, and how <br />you would have received the bid bond if there is one. Such as if they will <br />both have to be together or if they can be separate. <br />Response: No alternates are included in the Bid Tab; therefore, a bid <br />bond is required for the entire project. <br />American Enqineerinq: <br />a) Bid Item #7 is called "Relocate powerllight poles." From the text of <br />Addendum No.3, I understood that we were to bid removal of light poles, <br />not relocate. Please clarify? <br />Response: The overhead electrical distribution system including the <br />power and light poles will be removed once the underground system <br />is energized. No relocation of power/light poles will be required. <br />b) The bid item to mill and resurface the bridge (the old bid form item #17) <br />has been deleted. Where are we to include this work or has it been <br />deleted? <br />Response: The work has been deleted. <br />c) The answer to SE Engineering's question Item band Downrite <br />Engineering's question Item a seem to contradict each other. Based on <br />the revised bid form, I assume that we are to demolish and remove the <br />pavers from the site in Bid Item #4 and install a plan 6" concrete slab to <br />replace it. Is this correct? <br />Response: Saw cut all driveways at the right of way line; remove and <br />dispose of all material; replace driveways with 6" concrete slab with <br />woven wire mesh as shown on the revised plans. Note: pavers are <br />to be salvaged for possible repair during construction. Excess may <br />be retained at the option of the owner. <br />d) On the revised bid form, Item #21 "Pavement seam joint at bridge <br />location" has been added. What is the specification for this "seam joint"? <br />Is this required at both bridges or only one of them? <br />Response: All the bridges are included. EE FDOT Index 2100 Sheets <br />1 thru 3 for details. <br />e) On the revised bid form Item #76, Allowance Account, is the correct <br />amount $500,000.00 or $5,000,000.00? <br />Response: The correct amount is $500,000.00. <br /> <br />00900-2 <br /> <br />05-4893 <br />