Laserfiche WebLink
<br />r <br /> <br />4.4.2 It is expressly agreed that no adjustment in the Contract Time or Contract Amount shall be <br />permitted, however, in connection with a concealed or unknown condition which does not differ <br />materially from those conditions disclosed or which reasonably should have been disclosed by <br />the Contractor's (1) prior inspections, tests, reviews and preconstruction investigations for the <br />Project, or (2) inspections, tests, reviews and preconstruction inspections which the Contractor <br />had the opportunity to make or should have performed in connection with the Project. <br /> <br />4.5 Claim for Additional Cost <br /> <br />4.5.1 If the Contractor makes a Claim for an increase in the Contract Amount, written notice as <br />provided herein shall be given before proceeding to execute the Work. In addition to all other <br />requirements for notice of a Claim, said notice shall detail and itemize the amount of all Claims <br />and shall contain sufficient data to permit evaluation of same by City. <br /> <br />4.6 Claims for Additional Time <br /> <br />4.6.1 If the Contractor makes a Claim for an extension in the Contract Time, written notice as <br />provided herein shall be given. In addition to other requirements for notice of a Claim, <br />Contractor shall include an estimate of the probable effect of delay upon the progress of the <br />Work. In the case of a continuing delay, only one Claim is necessary. Subject to other provisions <br />of the Contract, the Contractor may be entitled to an extension of the Contract Time (but no <br />increase in the Contract Amount) for delays which directly affect the project's critical path, <br />arising from unforeseeable causes beyond the control and without the fault or negligence of the <br />Contractor, Subcontractors or suppliers as follows: <br /> <br />.1 labor disputes and strikes (including strikes affecting transportation), that do, in <br />fact, directly and critically affect the progress of the Work; however, an extension of Contract <br />Time on account of an individual labor strike shall not exceed the number of days of said strike: <br /> <br />.2 acts of God, tornado, fire, hurricane, blizzard, earthquake, or typhoon that damage <br />completed work or stored materials <br /> <br />.3 unusually severe and abnormal inclement weather; however, the Contract Time <br />will not be extended due to normal inclement weather. The time for performance of this <br />Contract, as stated in the Contract Documents, includes an allowance for calendar days, which <br />may not be available for construction out of doors. For the purposes of this Contract, the <br />Contractor agrees that this allowance of calendar days per month is to be considered as normal <br />inclement weather. Unless the Contractor can substantiate to the satisfaction of the City that <br />there was greater than normal inclement weather considering the full term of the Contract Time <br />using a ten year average of accumulated record mean values from climatological data compiled <br />by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration for the <br />locale of the Project, and that such alleged greater than normal inclement weather actually <br />delayed the Work or portions thereof which had an effect upon the Contract Time, the Contractor <br />shall not be entitled to an extension of time. If the total accumulated number of calendar days <br />lost due to inclement weather, from the start of Work until Substantial Completion, exceeds the <br />total accumulated number to be expected for the same period from the aforesaid table, time for <br /> <br />"'", <br /> <br />22 <br /> <br />") <br />j <br />