SECTION 0 13 10 <br />CONSTRUCTION SCHEDULES <br />PART 1 - GENERAL <br />1.01 REQUIREMENTS INCLUDED <br />A. Promptly after Award of the Contract and within ten days after the effective date of the <br />Agreement, prepare and submit to the Engineer estimated construction progress <br />schedules for the work, with sub - schedules of related activities which are essential to its <br />progress. <br />B. Submit revised progress schedules on a monthly basis. <br />C. No partial payments shall be approved by the Engineer until there is an approved up to <br />date construction progress schedule on hand. <br />D. The Contractor shall designate an authorized representative of his firm who shall be <br />responsible for development and maintenance of the schedule and of progress and <br />payment reports. This representative of the Contractor shall have direct project control <br />and complete authority to act on behalf of the Contractor's schedule. <br />1.02 RELATED REQUIREMENTS <br />A. Section 01010: Summary of Work. <br />B. Section 01152: Applications for Payment <br />C. Section 01200: Project Meetings. <br />D. Section 01340: Shop Drawings, Working Drawings and Samples. <br />1.03 FORM OF SCHEDULES <br />A. Prepare schedules for submittal each month with pay request. The form of the schedule <br />is to be MicrosoftTM Project 4.1a or approved equal. The Schedule is to indicate work <br />completed to date and additions to or deletions from the schedule. <br />1. Provide separate horizontal bar or CPM for each trade or operation within each <br />structure or item. <br />2. Horizontal time scale: In weeks from start of construction and identify the first <br />work day of each month. <br />3. Scale and spacing: To allow space for notations and future revisions. <br />4. Minimum sheet size: 24 inches x 36 inches. <br />06/05 01310 -1 03- 4138.B <br />