1.02 RELATED REQUIREMENTS <br />' A. Section 01600: Material and Equipment <br />B. Section 01720: Project Record Documents <br />' C. Designate in the construction schedule, or in a separate coordinated schedule, the dates for <br />submission and the dates that reviewed Shop Drawings, Working Drawings and Samples <br />will be needed. <br />1.03 CONTRACTOR'S RESPONSIBILITY <br />' A. It is the duty of the Contractor to check all drawings, data and samples prepared by or for <br />him before submitting them to the Engineer for review. Each and every copy of the <br />Drawings and data shall bear Contractor's stamp or will be returned to the Contractor for <br />conformance with this requirement. Shop drawings shall indicate any deviations in the <br />submittal from requirements of the Contract Documents. <br />B. Determine and verify: <br />1. Field measurements <br />2. Field construction criteria <br />3. Catalog numbers and similar data <br />4. Conformance and Specifications <br />C. The Contractor shall furnish the Engineer a schedule of Shop Drawing submittals fixing <br />the respective dates for the submission of shop and working drawings, the beginning of <br />manufacture, testing and installation of materials, supplies and equipment. This schedule <br />shall indicate those that are critical to the progress schedule. <br />D. The Contractor shall not begin any of the work covered by a drawing, data, or a sample <br />returned for correction until a revision or correction thereof has been reviewed and <br />returned to him, by the Engineer approved. <br />E. The Contractor shall submit to the Engineer all drawings and schedules sufficiently in <br />advance of construction requirements to provide no less than twenty -one (21) calendar <br />days for checking and appropriate action from the time the Engineer receives them. <br />F. The Contractor shall submit three (3) copies of descriptive or product data submittals to <br />complement shop drawings for the Engineer plus the number of copies that the Contractor <br />requires. The Engineer will retain three (3) sets. All blueprint shop drawings shall be <br />submitted with one (1) set of reproducible and four (4) sets of print. The Engineer will <br />review the drawings and return to the Contractor the set of marked -up drawings with <br />appropriate review comments. <br />06/05 01340 -2 03- 4138.13 <br />