Laserfiche WebLink
11. Maintenance of quality standards. <br />12. Pending changes and substitutions. <br />13. Review proposed changes for: <br />a. Effect on Construction Schedule and on a completion date. <br />b. Effect on other contracts of the Project. <br />14. Other business. <br />15. Construction schedule. <br />16. Critical /long lead items. <br />F. The Contractor is to attend progress meetings and is to study previous <br />meeting minutes and current agenda items, in order to be prepared to <br />discuss pertinent topics such as deliveries of materials and equipment, <br />progress of work, etc. <br />G. The Contractor is to provide a current submittal log at each progress <br />meeting in accordance with Section 01340. <br />PART 2 - PRODUCTS (Not Used) <br />PART 3 - EXECUTION (Not Used) <br />END OF SECTION <br />06/06 01200 -4 03-4138.0 <br />