Laserfiche WebLink
<br />· Construction Schedule <br />Contractor's Schedule of Values <br />· List of material suppliers <br />· Itemized breakdown of anticipated equipment rates. Overhead and profit shall not be <br />included. <br /> <br />7.2 Contract Sum <br /> <br />7.2.1 The City shall compensate Contractor for all Work described herein and in the Contract <br />Documents the Contract Sum set forth in the Contract for Construction, subject to <br />additions and deletions as provided in the Contract. <br /> <br />7.3 Schedule of Values <br /> <br />7.3.1 Within fifteen (15) days after receipt of the Notice to Proceed, the Contractor shall submit <br />to the City's Representative a revised schedule of values allocated to various portions of <br />the Work, prepared in such form and supported by such data to substantiate its accuracy <br />as the City's Representative may require. The schedule of values MUST be approved by <br />the City. This schedule, unless objected to by the City's Representative, shall be used as <br />a basis for reviewing the Contractor's Applications for Payment. The values set forth in <br />such schedule shall not be used in any manner as fixing a basis for additions to or <br />deletions from the Contract Sum. The Schedule of Values is strictly for payment <br />allocation and shall not be used to establish prices. <br /> <br />7.4 Applications for Payment <br /> <br />7.4.1 Progress payments shall be made on account of materials and equipment delivered to <br />the site and incorporated in the Work. No payments will be made for materials and <br />equipment stored at the Project site but not yet incorporated into the Work. <br /> <br />7.4.2 If approved in writing and in advance by City, progress payments may be made on <br />account of materials and equipment delivered and suitably stored at the site for <br />subsequent incorporation in the Work. City may in its sole discretion refuse to grant <br />approval for payments for materials and equipment stored at the Project site but not yet <br />incorporated in the Work. Any approval by City for payment for materials and equipment <br />delivered and suitably stored at the site for subsequent incorporation in the Work shall be <br />conditioned upon Contractor's demonstrating that such materials and equipment are <br />adequately protected from weather, damage, vandalism and theft and that such materials <br />and equipment have been inventoried and stored in accordance with procedures <br />established by or approved by the City. Nothing in this clause shall imply or create any <br />liability on the part of the City for the Contractor's inventory and storage procedures or for <br />any loss or damage to material, equipment or supplies stored on the site, whether <br />incorporated into the work or not. In the event any such loss or damage occurs, the <br />Contractor remains solely responsible for all costs associated with replacement of the <br />affected materials, supplies and equipment including labor and incidental costs, and shall <br />have no claim against the City for such loss. <br /> <br />7.4.3 All applications for payment MUST be made on a standard AlA payment application form <br />acceptable to the City Representative and must contain the PO number and other project <br />information. All payment applications must include Original releases of Liens from all <br />suppliers, materialmen, subcontractors, and the Prime Contractor. Applications will not <br />be processed without all pertinent back-up documentation as required by the City's <br />Representative. <br /> <br />25 <br />