Laserfiche WebLink
Estimated Construction Schedule <br /> Phase 1 -Parking Garage and Pool Deck Renovation-April 2017 to January 2018 <br /> o Submit for Building Permits April let 2017 <br /> o Bid Release date April 18'2017 <br /> o Bid Award date June 18'2017 <br /> o Building Permit June 15t 2017 <br /> • Phase 1 start construction-June 15t 2017 <br /> • Phase 1 certificate of occupancy-February 15th 2018 <br /> • Phase 2-South Tower construction-February 2018 to November 2019 <br /> o Submit for Building Permits October 15th. 2017 <br /> o Bid Release date Oct 15t 2017 <br /> o Bid Award date January 15t 2018 <br /> o Building Permit Jan 15th 2018 <br /> • Phase 2 Start construction-February 14 2018 <br /> • Phase 2 Certificate of occupancy-November 2019 <br /> • Phase 3 West Tower construction-April 2020 to November 2021 <br /> o Submit for Building Permits September 1st 2018 <br /> o Bid Release date February 14 2019 <br /> o Bid Award date.July 18t 2019 <br /> o Building-Permit February 1st 2019 <br /> • Phase 3 Start construction-August 1812019 <br /> • Phase 3 Certificate of occupancy-April 1812021 <br /> Note Phase 3 construction is dependent on sales and occupancy of Phase 2 tower. <br /> • <br />