"If Contractor fails within ten (10) calendar days after written notice of Engineer..." <br /> ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION <br /> In the first sentence of Paragraph 14.02.A.1., change the phrase "At least twenty days before <br /> each progress payment is scheduled (but not more often than once a month), ..." to read: <br /> "By no later than the first day of the month, ...". <br /> Following Paragraph 14.02.A.3 add: <br /> 4. An original Partial Release of Lien is required from the General <br /> Contractor along with the application for Payment No. 1 and for each <br /> subsequent application thereafter. For each application for payment <br /> (excluding Application No. 1) the Contractor shall submit with the <br /> application Partial Releases of Liens for all Notice to Owners that have <br /> been received for the project by the Owner and Engineer". <br /> 5. With each Application for Payment, the Contractor shall submit supporting <br /> records and other evidence, in a form and amount acceptable to the City <br /> and the Engineer, to demonstrate the expenses incurred and the Work <br /> performed. This shall include, but not be limited to documentation related <br /> to the purchase of Owner-Provided Material and the reduction in the <br /> Contract Sum as a result of such expenditures. <br /> 6. Each application for Payment shall be based on the most recent schedule <br /> of values submitted by Contractor in accordance with the Contract <br /> Documents. The schedule of values shall allocate the entire guaranteed <br /> maximum Contract Price among the various portions of the Work, except <br /> that the Contractor's Fee shall be shown as a separate item. The <br /> schedule of values shall be prepared in such form and supported by such <br /> data to substantiate its accuracy as the Engineer may require. This <br /> schedule, unless objected to by the Engineer, shall be used as a basis for <br /> reviewing the Contractor's Applications for Payment. <br /> 7. Applications for payment shall show the percentage of completion of each <br /> portion of the Work as of the end of the period covered by the Application <br /> for Payment. The percentage of completion shall be the lesser of: (1) the <br /> percentage of that portion of the Work which has actually been <br /> completed; or (2) the percentage obtained by dividing (a) the expense <br /> that has actually been incurred by the Contractor on account of that <br /> portion of the Work for which the Contractor has made or intends to make <br /> actual payment prior to the next Application for Payment by (b) the share <br /> of the Contract Price allocated to that portion of the Work in the schedule <br /> of values. <br /> 8. Subject to the provisions of the Contract Documents, the amount of <br /> progress payments shall be computed as follows: <br /> a) take that portion of the Contract Price properly allocable to the <br /> computed Work as determined by multiplying the percentage of <br /> completion of each portion of the Work in the schedule of values. <br /> Pending final determination of the costs to the Owner of changes <br /> in the Work, amounts not in dispute shall be included in the <br /> Application for Payment along with Change Order, Work Change <br /> 08/12 00800-7 11-4179 <br />