Item 5) <br /> Iron Sky is proposing the following Project Schedule: <br /> Weeks 1-3 <br /> - Project kick off meeting <br /> - Schedule resources <br /> - Visit planned rooftops, radio locations and pole locations to obtain any remaining information <br /> required for rooftop agreements and permitting <br /> - Identify alternate equipment locations at no additional cost to the City <br /> - Schedule permitting meetings with city, county and private property owners/ property managers <br /> - Complete documentation for permits and rooftop agreements <br /> Weeks 4 & 5 <br /> - Permitting and rooftop agreement meetings <br /> - Revise installation plans as necessary to achieve agreements and permits <br /> - Complete detailed design and Bill of Material (dependent upon progress of permits and rooftop <br /> agreements). <br /> (Note:Permitting and rooftop agreement progress is only partially controlled by Iron Sky. The time <br /> required to obtain all rooftop agreements and permits could be more or less than the time allocated in <br /> this timeline. The remainder of the timeline will be dependent upon achieving the necessary agreements <br /> and permits required to proceed. Material procurement and staging will not begin until all permits have <br /> been secured and project schedule will be extended the appropriate number of days to reflect any <br /> permitting delays that extend beyond week 5). <br /> Weeks 6-9 <br /> - Material procurement and staging <br /> Weeks 10— 14 <br /> - Equipment installation, alignment and adjustment <br /> Week 15 <br /> - System integration with LEARN <br /> - Remote client application installed on mobile terminals <br /> - Create user accounts <br /> - HotList integration and approvals <br /> Weeks 16 & 17 <br /> - User training <br /> Week 18 <br /> - User acceptance <br /> Item 6) <br /> 1773 Westborough Drive, Suite 223, Katy,TX 77449 <br />