the Contractor may be required to submit a request for a Change Order proposal. Where the <br /> Contractor is notified of the position that the Field Directive is within the scope and the <br /> Contractor disagrees, the Contractor shall notify the City that the Contractor reserves the right <br /> to make a claim for the time and monies based on the Field Directive. At no time shall the <br /> Contractor refuse to comply with the directive. Failure to comply with the directive may result <br /> in a determination that the Contractor is in default of the Agreement. <br /> ARTICLE 8. CHANGE ORDERS <br /> 8.1 Changes in the quantity or character of the Work which are not properly the subject of Field <br /> Directives shall be authorized only by Change Orders approved in advance and issued in accordance <br /> with the guidelines of the City. <br /> 8.2 All changes to the Work must be pre-approved in writing, in advance, by the City in <br /> accordance with the value of the Change Order or the calculated value of the time extension. In the <br /> event Contractor fails to follow this procedure and performs additional Work without first obtaining <br /> pre-approval in writing by the City, the Contractor shall not be entitled to any additional monies in <br /> connection with the additional Work performed. <br /> 8.3 In the event satisfactory adjustment cannot be reached for any item requiring a change in the <br /> Contract Amount, the City reserves the right at its sole option to either terminate the Agreement as <br /> it applies to the items in question and make such arrangements as may be deemed necessary to <br /> complete the disputed work; or may submit the matter in dispute as set forth in the dispute resolution <br /> procedures set forth in this Agreement. <br /> 8.4 On approval of any change increasing the Contract amount, Contractor shall ensure that the <br /> Bonds are increased accordingly. <br /> ARTICLE 9. SCOPE OF WORK MODIFICATION PROCEDURES <br /> 9.1 OWNER INITIATED MODIFICATIONS <br /> The City will issue a detailed description of proposed changes in the Work that may require an <br /> adjustment(s)to the Contract Amount or Contract Time. If necessary, the description will include <br /> supplemental or revised drawings and specifications. Subsequent to notification of modifications <br /> in the Work by City, Contractor shall submit a quotation estimating cost adjustments to the <br /> Contract Amount and/or the Contract Time necessary to execute the change. Contractor shall <br /> include the following information when responding: <br /> • Include a list of quantities of products required or eliminated and unit costs, with total <br /> amount of purchases and credits to be made. If requested, furnish survey data to <br /> substantiate quantities. <br /> • Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade <br /> discounts. <br /> • Include costs of labor and supervision directly attributableto the change. <br /> • Include an updated contractor's construction schedule that indicates the effect of the <br /> change, including but not limited to, changes in activity duration, start and finish times, <br /> and activity relationship. <br /> 8 <br />