� Craig A. Smith & Associates, Inc.
<br />Engineers • Surveyors • Subsurface Utility Engineering
<br />30 Subsurface Imaging • Utility Coordination
<br />SECTION E1 -QUALIFICATION
<br />INFORMATION AND ASSIGNED
<br />PERSONNEL
<br />•Hardee County - Wauchula HIiis Water & Sanitary Sewer Improvements -Phase IV, Wauchula,
<br />Florida
<br />Status: Completed 2017
<br />Prime Consultant: CAS
<br />Key CAS Staff: Gene R. Schriner, Greg Giarratana, Keith Schriner, Robert D. KeenerScope of Work: Survey, design, contract document development, permitting, bidding, construction
<br />management and observation through project clos�ut for the installation of approximately
<br />6,125 linear feet of 8" water main and 5,277 linear feet of 8" gravity sanitary sewer including
<br />connection to 51 private residences and the decommissioning of septic tanks. This project was
<br />completed on time and within budget.
<br />Pro/ect Challenges & Approach: Community outreach and coordin ation with residents for water
<br />and sewer service connections was essential for the successful completion of this project. Also
<br />close coordination with the contractor during construction was necessary in order to ensure that
<br />road damage/restoration was minimized.
<br />Design Cost Clncludlng Construction Management}: $189,628
<br />Construction Cost: $1,249,013
<br />•City-County Publlc Works Authority (CCPWA} -Avenue R Wastewater Collectlon/Conveyance
<br />System Improvements, Moore Haven, Florida
<br />Status: Completed 2017
<br />Prime Consultant: CAS
<br />Key CAS Staff: Gene R. Schriner, Keith Schriner, Greg Giarratana, Robert KeenerScope of Work: Survey, design, preparation of construction plans and contract document
<br />development, permitting, bidding, construction management, const ruction observation through
<br />project closeout/start-up services for the installation 1,200 linear feet of 8-inch FM replacement,
<br />one (1) 180-linear foot directional drill, seven (7) sanitary sewer manhole structures, 2,800 linear
<br />feet of gravity sewer, thirty-two (32) service laterals, fifty-two (52) clean-outs for residential hook
<br />ups, roadway reconstruction. This project is a continuation of an existing system and part of a
<br />gravity sewer collection master plan which addresses infrastructure needs within the southeastern
<br />residential area of the City. This project was completed on time and within budget.
<br />Design Cost {Including Construction Management}: $47,280
<br />Construction Cost: $426,787
<br />•Mlccosukee Tribe of Aorlda -Water Distribution System Improvements, Miami Dade, Aorida
<br />Status: Completed 2015
<br />Prime Consultant: CAS
<br />Key CAS Staff: Gene R. Schriner, Greg Giarratana, Robert KeenerScope of Work: Survey, design, permitting, contract development, bidding services and construction
<br />oversight for the installation of 15,000 LF of 12" water main which included eight (8) 12• diameter
<br />horizontal dlrectlonal drllllng installations, one (1) s• horizontal dlrectlonal drill and new water service
<br />lines to residences. This project was completed on time and within budget.
<br />Design Cost: (Including Construction Management} $516,000
<br />Construction Cost: $2,580,000
<br />21045 Commercial Trail, Boca Raton, FL 33486 • Ph: 561-314-4445 • www.craigasmith.com • LB3110
|