Continuous Schedule Monitoring <br />CAP does not consider a schedule to be a document that is prepared once and then set aside. The Project Manager <br />will continuously monitor project progress against established milestones and completion dates. <br />During the course of the assignment, the Project Manager will evaluate: <br />Progress against scheduled activities and milestones; <br />Status of required technical information and field data; <br />Staff availability and workload; <br />Interdisciplinary coordination requirements; <br />Outstanding Client decisions or comments; <br />Third-party coordination requirements; <br />Quality control and review activities; <br />Changes in scope or project priorities; and <br />Potential impacts to the final completion date. <br />This ongoing monitoring allows CAP to identify schedule risks early rather than waiting until a deadline is approaching <br />Proactive Management of Schedule Risks <br />CAP takes a proactive approach to potential schedule impacts. When the Project Manager identifies an activity that <br />may affect the established schedule, the issue will be evaluated immediately to determine its cause, potential impact, <br />and available corrective measures. <br />Depending on the circumstances, CAP may: <br />Reallocate personnel to critical activities; <br />Add qualified staff to accelerate production; <br />Adjust the sequence of project activities; <br />Prioritize critical-path tasks; <br />Increase internal coordination; <br />Accelerate technical or quality control reviews; <br />Conduct additional coordination meetings; <br />Expedite preparation of interim deliverables; or <br />Coordinate with the City regarding information or decisions needed to maintain progress. <br />The City's Project Manager will be notified promptly of significant issues that could affect the established completion <br />date, along with CAP's recommended corrective action and anticipated resolution. <br />Our objective is to identify and resolve schedule issues before they become deadline issues. <br />RFQ No. 26-07-014.2 - Overall Project Organization <br />RFQ No. 26-07-01 <br />Q: How will CAP organize its project team, resources, responsibilities, and <br />coordination to successfully complete assignments for the City? <br />C.A.P. Engineering, Inc. <br />84