RFQ # 26-07-01 | CITY OF SUNNY ISLES BEACH 119
<br />CES CONSULTANTS, INC.
<br />Nikolai Gage is a professional engineer with 12 years of experience in civil infrastructure design,
<br />construction management, and condition assessment, with a focus on water and wastewater systems.
<br />His work spans civil site development, yard piping design, utility relocation, and surface restoration
<br />for treatment plant upgrades and pump station rehabilitation. He has performed detailed inspections
<br />and assessments of mechanical, electrical, and structural components of sewer infrastructure,
<br />supported asset management and capital planning efforts, and managed construction activities
<br />including scheduling, permitting, and coordination with regulatory agencies. His technical expertise,
<br />field insight, and collaborative approach consistently deliver practical, cost-effective solutions that
<br />help clients achieve project goals, maintain compliance, and improve infrastructure performance.
<br />NE 191st Street Drainage & Roadway Improvements, Aventura, FL: Project Engineer. Provides
<br />project management, design, permitting, bid-phase support, and construction coordination for
<br />drainage, roadway elevation, and resilience improvements within a low-lying corridor prone to
<br />recurrent flooding. The project includes a new stormwater collection system, hydraulic modeling,
<br />utility coordination, water quality infrastructure, traffic signal upgrades, and public engagement to
<br />improve mobility, emergency access, and long-term flood resilience.
<br />Rehab/Replacement of 48”/54” Force Main from SE 9th & 10th Avenue to GTL WWTP Design-
<br />Build, Fort Lauderdale, FL: Project Engineer. The project involves rehabilitation or replacement of
<br />15,150 LF of existing 48- and 54-inch force main and installation of 8,220 LF of new 48-inch force
<br />main, totaling 23,370 LF of pipeline improvements. The project includes design, permitting, utility
<br />relocations, construction procurement assistance, and limited construction support to restore reliable
<br />wastewater conveyance to the George T. Lohmeyer Wastewater Treatment Plant (GTL WWTP).
<br />Water & Sewer Infrastructure Master Planning (Contract 201307), Homestead, FL: Project Engineer.
<br />Assists with master planning for the City’s water distribution and wastewater collection systems,
<br />including capacity analysis, future development impacts, lift and pump station evaluations, and
<br />interconnections. The project includes development of a prioritized capital improvement program
<br />with phased recommendations, cost estimates, performance criteria, and long-term strategies to
<br />improve system resilience, operational efficiency, and infrastructure planning.
<br />MDWASD Engineering, Design & Related Services for the Local Pump Station Improvement
<br />Program, $34M, Miami-Dade County, FL: Project Manager/Project Engineer. Manages the inspection,
<br />evaluation, analysis, and design of multiple sanitary sewer lift stations ranging from 20 to 60 HP
<br />and associated force mains, including the conversion of wet well/dry well systems to submersible
<br />stations. The work addresses FEMA base flood elevation requirements, operational and maintenance
<br />needs, structural reuse of existing facilities, constructability, and cost-effective infrastructure
<br />improvements. Assignments: PS0023, PS0803, PS0132, PS0549, PS1034, and PS0704 Relocation.
<br />MDWASD Pump Station Improvement Program (PSIP), Miami-Dade County, FL: Construction Project
<br />Manager/Junior Engineer. Provided engineering and construction management services for the
<br />rehabilitation and upgrade of more than 70 sewer pump stations and associated force mains, including
<br />gravity sewer redirection and a 24-inch DIP microtunnel beneath the CSX ROW. Responsibilities
<br />included field assessments, technical reports, remedial action plans, quantity takeoffs, permitting and
<br />construction coordination, schedule and payment reviews, change order evaluations, construction
<br />meetings, pressure testing, concrete placement, and pump station start-up. Also served as Field
<br />Inspector for the 54-inch HDPE Redundant Sanitary Sewage Force Main project in Miami Beach.
<br />NIKOLAI GAGE, PE
<br />Professional Engineer
<br />YEARS EXPERIENCE
<br />12
<br />EDUCATION
<br />MS, Engineering Management,
<br />Florida International University,
<br />2014
<br />BS, Civil Engineering, Florida
<br />International University, 2012
<br />REGISTRATIONS &
<br />CERTIFICATIONS
<br />Florida Professional Engineer
<br />#85070, 2018
<br />SOFTWARE/TECHNICAL SKILLS
<br />AutoCAD
<br />Microsoft Office Suite
|