<br />Proposed Schedule of Surveying & Mapping Services
<br />Phase Typical Duration Anticipated Services
<br />Survey Scoping 1–3 business days
<br />Confirm limits, intended use, accuracy, datum, control, property
<br />research, utility requirements, access needs, deliverable format, and schedule.
<br />Records Research
<br />and Reconnaissance 2–5 business days
<br />Review plats, deeds, right-of-way maps, benchmarks, prior
<br />surveys, utility records, control data, and available GIS
<br />information; conduct field reconnaissance.
<br />Control and Field
<br />Data Collection 1–3 weeks
<br />Establish or verify control and perform conventional, GNSS,
<br />LiDAR, topographic, boundary, hydrographic, utility, construction,
<br />or other required field services.
<br />Processing and
<br />Production 1–2 weeks
<br />Process observations and point clouds; complete closures and
<br />adjustments; prepare maps, DTMs, CADD files, sketches, legal descriptions, and GIS deliverables.
<br />Professional Review
<br />and Delivery 2–5 business days
<br />Complete independent QA/QC, resolve comments, verify
<br />standards compliance, and issue signed-and-sealed deliverables
<br />when required.
<br />Construction and
<br />Closeout
<br />Duration of
<br />construction
<br />Review shop drawings, submittals, RFIs, change requests, and
<br />payment documentation; provide site observations, technical
<br />support, record drawings, and closeout services.
<br />Scheduling will depend on assignment limits, access, traffic and pedestrian conditions, records availability,
<br />feature density, required utility investigations, water access, and the level of detail required. Field data
<br />collection and office processing may proceed concurrently to support accelerated assignments.
<br />Transportation / Transit / Traffic Engineering
<br />Transportation, transit, and traffic engineering are core CTS practices. CTS provides in-house expertise
<br />in traffic operations and safety, transportation planning, traffic forecasting and modeling, signalization,
<br />ITS and TSM&O, Complete Streets, transit planning, multimodal facilities, traffic calming, parking and
<br />curbside operations, data collection, signing and pavement markings, roadway lighting, maintenance
<br />of traffic, cost estimating, and construction documents. Our personnel have supported municipalities,
<br />counties, FDOT Districts 4 and 6, Miami-Dade County and TPO, Broward County Transit, MPOs, and
<br />regional transportation agencies through continuing-services contracts and individual assignments
<br />ranging from focused traffic studies to systemwide transportation and transit programs.
<br />CTS combines conventional transportation engineering with transit operations, GIS, data analytics,
<br />and implementation planning. Our capabilities include corridor and subarea planning, traffic impact
<br />and operational analysis, travel-demand forecasting, microsimulation, intersection control evaluations,
<br />signal warrants and timing, crash and safety analysis, parking-demand and utilization studies, curbside
<br />management, transportation demand management, school-zone evaluations, pedestrian and bicycle
<br />studies, ADA and accessibility reviews, and development of performance measures and prioritization
<br />tools. CTS also provides field data collection, including traffic counts, turning movements, speed and
<br />travel-time studies, queue observations, pedestrian and bicycle counts, transit ride checks, passenger
<br />counts, and stop- and route-level operational assessments.
|