RFQ # 26-07-01 CONTINUING PROFESSIONAL ARCHITECTURAL AND ENGINEERING CONSULTING SERVICES (CCNA)
<br />DISCIPLINE CATEGORY #4. ELECTRICAL ENGINEERS
<br />50
<br />Work-Plan Step SGM Action Control / Output City Interface
<br />2. Kickoff and scope validation Define goals, stakeholders, success criteria, deliverables, acceptance requirements, budget basis, schedule, and communications. For complex assignments, conduct an Owner’s Project Requirements and design-criteria workshop.
<br />Scope matrix, work breakdown structure, responsibility matrix, baseline schedule, decision log, and, when applicable, Owner’s Project Requirements.
<br />Approve scope, priorities, performance criteria, decision dates, review durations, and meeting cadence.
<br />3. Existing conditions and risk
<br />Review records; prepare the asset inventory and inspection checklist; field verify equipment, ratings, capacities, condition, routing, clearances, and access; and coordinate utilities, operations, code and AHJ requirements, technology platforms, coastal exposure, flood conditions, and resilience requirements.
<br />Existing-condition asset inventory, photographs, field markups, calculations, prioritized deficiencies, risk register, and permit matrix.
<br />Validate operational constraints, outages, stakeholders, observed discrepancies, and preferred alternatives.
<br />4. 30% concept/preliminary Develop alternatives and the recommended basis of design; prepare the preliminary estimate and schedule update.
<br />30-percent package, alternatives and life-cycle comparison, estimate, and updated risks.
<br />Select the solution and close concept-level comments before further development.
<br />5. 60% design development Advance calculations, layouts, one-lines, controls, specifications, commissioning requirements, coastal-resilience measures, and cross-discipline interfaces.
<br />60-percent package, coordinated model and drawings, estimate reconciliation, schedule update, and comment log.
<br />Confirm systems, equipment strategy, City standards, and unresolved decisions.
<br />6. 90% construction documents
<br />Complete a bid-ready package; perform detailed constructability, code, cost, schedule, commissioning, coastal-resilience, and independent QA/QC reviews. Conduct a formal interdisciplinary-review out-brief for complex assignments.
<br />90-percent package, QA/QC record, permit pre-check, detailed estimate, schedule update, assigned corrective actions, and closed comment matrix.
<br />Resolve final scope and bid and permit decisions.
<br />7. 100%/permit/bid Close all comments; complete Engineer of Record review and signatures and seals; submit for permits; and support procurement and addenda.
<br />Issued package, permit log, bid and RFI log, final pre-bid estimate, and approved baseline or updated schedule.
<br />Accept documents; authorize permit and bid actions and all formal changes.
<br />8. Construction administration Review RFIs, submittals, pay applications, changes, field conditions, testing, commissioning, and schedule effects.
<br />Construction-administration log, site reports, recommendation records, change log, deficiency log, and updated forecast.
<br />Approve changes, payments, corrective actions, and milestone decisions.
<br />9. Closeout and improvement Verify punch-list completion, final permit approvals and cards, testing and commis-sioning reports, operator training records, operation and maintenance manuals, war-ranties and responsible contacts, record drawings, corrected CADD files, three-di-mensional data, and the status of changes and allowances.
<br />Accepted closeout matrix and document set, com-pleted training and testing records, warranty log, com-plaint and issue closure, and performance summary.
<br />Confirm final accep-tance and carry lessons into the next task order.
|