<br /> <br />Page 2 <br /> <br />2.8. Saw cut, mill and Remove existing asphalt as shown the demolition plan in order to install <br />all required drainage, curbs and inlets. <br />2.9. Utilize an Excavator and crane and perform demolition and disposal of all required, <br />roadway, curbing, asphalt, signs, seawalls, concrete, etc. <br />2.10. Removal and stockpile all interfering pavers and signage <br />2.11. Remove and stockpile existing parking meters and signs <br />2.12. Removal of all pavement markings with Sand and Water Blasting <br />2.13. Perform clearing and grubbing <br />2.14. Mobilize the soil improvement subcontractor immediately following demolition. <br />2.15. Perform all necessary soil improvement in accordance with the soil improvement <br />contractors design specifications; as approved by the engineer, based on final geotechnical <br />conditions. It is expected that either soil mixing or chemical grouting will be used to <br />improve the soils; however, the subcontractor shall be prepared for either based on the <br />performance of the initial system chosen (in the event that chemical grouting does not <br />adequately improve the soils, the contractor will be prepared to change to soil mixing). <br />2.16. Bridge construction will begin once soil improvement is complete and approved. <br />2.17. Excavate saw cut and remove approximately 38 LF of existing concrete seawall at End <br />Bent #1 to allow for bridge construction. Protect seawall to remain in place during <br />construction, take care not to disturb the tie rods that must remain in place. <br /> <br />3. Foundation <br />3.1. Install approximately 96 LF of pile supported temporary crane trestle along centerline of <br />the bridge to Bent No. 3 <br />3.2. Utilize the Crane and Drilled shaft Rig to install a demonstration shaft at a sacrificial <br />location. Demonstration shaft shall be cut off to a minimum of 2 ft below finish grade. <br />Demonstration shaft shall be installed utilizing same equipment and procedure as the <br />production drilled shafts (as outlined below) <br />3.3. Working off the trestle; utilize the lattice boom crawler crane and vibratory hammer to <br />install to install the temporary pile supported falsework for drilled shaft installation. <br />3.4. Working off the trestle; utilize the lattice boom crawler crane and vibratory hammer to <br />install to install the 4 ea. 42” I.D. steel casing, casing shall be driven until it seats into <br />competent material. Cut the Drilled shaft casing off to the top of drilled shaft elevation. <br />3.5. After casing is installed, the Bauer BG25 Drilled shaft rig, will walk onto the trestle and <br />drill and clean out each drilled shaft. Spoils shall be loaded into sealed storage boxes for <br />dewatering then loaded onto dump trucks for disposal after drying. The Drilled shaft rig <br />will walk off of the trestle after the four shafts are complete. Ebsary’s drilled shaft <br />equipment shall be equipped to drill and clean out the 42” drilled shaft, at a minimum of <br />elevation of -83 NGVD. Ebsary shall be prepared to drill deeper in the event that issues <br />are encountered during installation. <br />3.6. Baffle boxes and settling tanks shall be set within reach of the 3” trash pump that will be <br />used to pump the water during concrete placement.