<br /> <br />Page 5 <br /> <br />concrete cap and the required beam seats and end walls. <br />5.5. After the concrete end bent cap has achieved 28 day strength and the MSE Wall has been <br />set under the bridge centerline, use the lattice boom crawler crane to set and temporarily <br />brace the 36” I-Beams and Rectangular Haunched Beams between End Bent 1 and Bent 2 <br />and End Bent 6 and Bent 5. <br />5.6. Once Bridge Concrete is complete and the MSE retaining wall is backfilled and <br />appropriately compacted to bottom of approach slab elevation, form and place the 1ft <br />thick approach slabs at each end of the bridge. Approach slabs shall be doweled into the <br />backwall and poured with the MSE wall coping. The approach slab shall have a step to <br />incorporate the 1¾” asphalt overlay and shall have a transverse broom finish on exposed <br />surfaces. Utilize Expanded Polystyrene cover over MSE wall at the Coping. <br />5.7. Install CIP concrete gutter between MSE coping and end bent cap. <br />5.8. Extend the 32” traffic railing, in accordance with the superstructure concrete after <br />approach slab and coping installation. <br />5.9. Place 1¾” Asphalt overlay in a single lift over approach slab <br /> <br />6. Superstructure <br />6.1. After the 36” I-Beams and Rectangular Haunched Beams are set on each span, cast in <br />place concrete crews will continue work, concurrently with the additional bridge work, to <br />form and place the auxiliary cast in place concrete which includes bracing, safety sleeves, <br />intermediate diaphragms, cheek walls, expansion dams, premoulded expansion materials, <br />roofing paper, end diaphragms, sidewalls and end bent backwalls. <br />6.2. Upon completion of each spans of auxiliary concrete, install the galvanized steel stay in <br />place deck forms. Beam Camber shall be monitored throughout the construction process <br />and shall be measured and compared to theoretical @ 120 days. All measurements shall <br />be compared to the predicted and beam build ups shall be incorporated, prior to stay in <br />place form installation, at the direction of the engineer. <br />6.3. Install overhang brackets for the deck pour outside of the outer and Rectangular Haunched <br />Beams. Install with overhangs large enough to install handrails and work platform outside <br />of bridge area. Overhang formwork will incorporate continuous v-groove on the bottom <br />of the overhang. <br />6.4. Install end forms for each span with screed rails mounted to the tops of the forms <br />6.5. Install deck reinforcing, expansion dams, bulkheads and 2” electrical conduit and required <br />junction boxes <br />6.6. Place cast in place concrete utilizing a 32 meter concrete pump and place the concrete <br />from the center of the span outward towards each bent. Grade will be checked after initial <br />placement to ensure the concrete final elevation takes into account for beam deflection. <br />Deck pour shall incorporate a 2% crown. <br />6.7. Finish deck concrete with Bidwell Screed and Floats. <br />6.8. After placing, curing and stripping the deck, form and place the light pole pilasters in <br />accordance with index 21200. Forming and placing shall incorporate the tie in to the 2”