<br /> Atlantic Isles Roadway and Utility Improvements
<br />Bid Estimated
<br />Item Descri tion Quantity Unit Unit Price Estimated Total
<br />30 Furnish & Install 18" RCP drainage pipe complete
<br /> (including but not limited to excavation, bedding,
<br /> backfill, compaction & restoration as per plans
<br /> and specifications) 325 LF $ 38.00 $ 12,350.00
<br />31 Furnish & Install 24" RCP drainage pipe complete
<br /> (including but not limited to excavation, bedding.
<br /> backfill, compaction & restoration as per plans
<br /> and specifications) 1,650 LF $ 47.00 $ 77,550.00
<br />32 Furnish & Install 30" RCP drainage pipe complete
<br /> (including but not limited to excavation, bedding,
<br /> backfill, compaction & restoration as per plans
<br /> and specifications) 720 LF $ 68.00 $ 48,960.00
<br />33 Ultralite Tideflex Check Valve 1 EA $8,900.00 $ 8,900,00
<br />34 Vortech-Model 5000 1 LS $ 39.000.00 $ 39,000.00
<br />E Senitsry Sewer System and Force Main per
<br /> WASD Standards/Spec
<br />35 F&I 8" PVC sanitary sewer complete (including
<br /> but not limited to excavation, bedding, backfill.
<br /> compaction & restoration as per plans and
<br /> specifications) 2,340 LF $ 38.00 $ 88,920,00
<br />36 F&I 8" DIP sanitary sewer complete (including but
<br /> not limited to excavation, bedding, backfill,
<br /> compaction & restoration as per plans and
<br /> specifications) 120 LF $ 50.00 $ 6,000,00
<br />37 F&I 10" PVC sanitary sewer complete (including
<br /> but not limited to excavation, bedding, backfill,
<br /> compaction & restoration as per plans and
<br /> specifications) 270 LF $52.00 $14,040.00
<br />38 F&I 12" PVC sanitary sewer complete (including
<br /> but not limited to excavation, bedding, backfill,
<br /> compaction & restoration as per plans and
<br /> specifications) 45 LF $ 60.00 $ 2,700,00
<br />39 Sanitary drop manholes 48" dia. 1 EA $ 2,650.00 $ 2,650.00
<br />40 Core drill existing manhole #24 1 EA $ 2,500.00 $ 2.500.00
<br />41 Sanitary manholes 48" dia, 22 EA $ 2,350.00 $ 51.700,00
<br />42 F&I 6" DIP force main complete (including but not
<br /> limited to excavation, bedding, backfill,
<br /> compaction & restoration as per plans and
<br /> specifications) 1,150 LF $37,00 $42.550.00
<br />43 F&I 8" DIP force main complete (including but not
<br /> limited to excavation, bedding, backfill,
<br /> compaction & restoration as per plans and
<br /> specifications) 50 LF $ 48.00 $ 2.400.00
<br />44 Miscellaneous sanitary PVC fittings 1 LS $ 7.440 00 $ 7 440 00
<br />45 Miscellaneous DIP valves and fittings 1 LS $g40000 $ g 400 00
<br /> .
<br />46 F&I 6" sanitary services laterals complete
<br /> (including but not limited to excavation, bedding,
<br /> backfill, compaction & restoration as per plans
<br /> and specifications) 62 EA $ 1,400.00 $ 86,800.00
<br />47 F&I 6" Force main bridge crossing as per detail on
<br /> addendum (Bridge No. A) 63 LF $ 638 75 $ 40 ?41 ?'i
<br />48 F&I 6" Force main bridge crossing as per detail on .
<br /> addendum (Bridge No, 8) 51 LF $ 638.75 $ 32 576 25
<br />OS/08-Addendum NO.5 00300-3 05-4893