<br /> E. RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT
<br /> (Complete one Section E for each key person.)
<br />2. NAME 13. ROLE IN THIS CONTRACT 14. YEARS EXPERIENCE 28
<br /> Matthew E. Meyer, P.E. Geotechnical Engineer a. TOTAL b. WITH CURRENT FIRM
<br /> 13 Y, yrs 10 Y, yrs
<br />15. FIRM NAME AND LOCATION (City and State) Langan Engineering & Environmental Services I Miami Lakes, Florida
<br />16. EDUCATION (DEGREE AND SPECIALlZA TlON) 17. CURRENT PROFESSIONAL REGISTRATION (STATE AND DISCIPLINE)
<br />Virginia Polytechnic Institute and State University, Master of Florida and West Virginia I FL #54630
<br />Science in Civil Engineering, (Geotechnical) 1995 PAOI Certified SCUBA Diver
<br />The Citadel (The Military College of South Carolina) Bachelor
<br />of Science in Civil Engineering, 1994
<br />18. OTHER PROFESSIONAL QUALIFICATIONS (Publications, Organizations, Training, Awards, etc.)
<br /> 19. RELEVANT PROJECTS
<br /> (1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> The Four Seasons Hotel & Tower, Miami, Florida PROFESSIONAL SERVICES I CONSTRUCTION (if applicable)
<br /> 2003
<br /> (3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE 121 Check if project performed with current firm.
<br />a. This development consists of a 66-story high rise hotel, condominium, and office building, a 20-story podium and 6-story garage, Assisted in the
<br /> geotechnical construction aspects of this project to include the following: (A) Full-time inspection, load testing and coordination of over 100, 6-ft
<br /> diameter polymer drilled shafts with lengths of 110ft to 135 ft. Installation techniques included: 1) uncased drilled shafts stabilized with polymer or
<br /> bentonite slurry, and 2) cased drilled shafts in the upper portions and slurry stabilized in the lower portions; (B) Dewatering consultation and field
<br /> inspection of tremie sealed sheeted excavations (cofferdams) to facilitate dewatering and subsequent placement of cap concrete up to 17 ft below
<br /> the qroundwater table. Cost of work: $1,300,000
<br /> (1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Met 2 and Met 3 Tower, Miami, Florida PROFESSIONAL SERVICES I CONSTRUCTION (if applicable)
<br /> On-going
<br />b. (3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE 121 Check if project performed with current firm.
<br />This development is to consist of a 1-billion dollar development including three high-rise structures ranging from 45-stories to 75-stories and
<br /> adjacent connecting garage/podium, theater structure. Performed a geotechnical engineering study and provided technical assistance throughout
<br /> the design/construction phases of this project. This project was initially designed to be supported on 125, 6-ft-diameter drilled shafts installed to
<br /> significant depths; however, due to significant advances in the local ACIP Piling industry, 36-inch-diameter, 1,200 ton piles were utilized for tower
<br /> support, Cost of work: $1,000,000 (phased)
<br /> (1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Solis Resort, Sunny Isles Beach, Florida PROFESSIONAL SERVICES I CONSTRUCTION (if applicable)
<br /> On-going
<br /> (3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE 121 Check if project performed with current firm.
<br />c. Technical Advisor. The project is under-construction and consists of a 55-story residential tower in the southern end of Sunny
<br /> Isles Beach. The foundation design for this project consists of the use of 30-inch-diameter, 145 ft to 150 ft long augered cast-in-
<br /> place (ACIP) piles extended beyond the compressible sand and weakly cemented layers typically encountered in the Sunny Isles
<br /> Beach area. The ACIP pile load testing program included the installation of a deep O-cell embedded jack, approximately 24 ft
<br /> above the tip of the test pile, The services also included the collection and testing of the near-surface materials for compatibility
<br /> with the beach sand, as part of the soil compatibility performed by the project civil engineer. Cost of work: $250,000
<br /> (1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Dolphin Stadium, Miami Gardens, Florida PROFESSIONAL SERVICES I CONSTRUCTION (if applicable)
<br /> On-going
<br />d. (3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE 121 Check if project performed with current firm.
<br />Designed and oversaw the construction of the foundation aspects of the expansion of the Dolphins Stadium for SuperBowl XXVI. The
<br /> implemented foundation systems consisted of footings on improved soils, high-capacity rock anchors and augered-cast-in-place piles. Cost of
<br /> work: $365.000
<br /> (1) TITLE AND LOCATION (City and State) (2) YEAR COMPLETED
<br /> Turnberry Ocean Colony Development, Sunny Isles Beach, Florida PROFESSIONAL SERVICES I CONSTRUCTION (if applicable)
<br /> 2007
<br /> (3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE 121 Check if project performed with current firm.
<br /> This development consists of twin 38-story towers and a connecting submerged 3-level parking garage. Assisted with the preparation of the
<br /> geotechnical engineering study report for the support of the towers on 420-ton. 24-inch-dia augercast piles and settlement related issues.
<br /> Provided construction oversight and project management during augercast load testing, production pile installation, and sheet pile installation.
<br /> Cost of work: $450,000
<br /> STANDARD FORM 330 (6/2004) PAGE 2