3. Scale and spacing: To allow space for notations and future <br />revisions. <br />4. Minimum sheet size: 24 inches x 36 inches. <br />B. Format of listings: The chronological order of the start of each item of <br />work for each structure. <br />C. Identification of listings: By major specification section numbers as <br />applicable and structure. <br />1.04 CONTENT OF SCHEDULES <br />A. Construction Progress Schedule: <br />1. Show the complete sequence of construction by activity. <br />2. Show the dates for the beginning of, and completion of, each major <br />element of construction in no more than a two -week increment <br />scale. Specifically list, but not limited to: <br />a. Receiving Materials <br />b. Pipeline Installations <br />C. Testing <br />d. Restoration <br />e. Startup <br />f. Record Drawings <br />g. Permits <br />h. Punch List <br />i. Owner Activities, Including Inspections <br />3. Show projected percentage of completion for each item, as of the <br />first of each month. <br />4. Show projected dollar cash flow requirements for each month of <br />construction. <br />5. Use of float suppression techniques such as preferential <br />sequencing or logic, special lead /lag logic restraints, and extended <br />activity times are prohibited, and use of float time disclosed or <br />implied by use of alternate float - suppression techniques shall be <br />shared to proportionate benefit of the Owner and Contractor. <br />6. Pursuant to above float- sharing requirement, no time extensions <br />will be granted nor delay damages paid until a delay occurs which <br />06/06 01310 -2 03- 4138.0 <br />