<br />Response: FPL will be undergrounding the electrical power <br />distribution to transformer pads, followed by extension of service to <br />62 homes. Power poles and light poles must remain in service until <br />the transfer from overhead to underground can take place. All <br />existing power poles will be removed after near the completion of the <br />project. The bid item will be revised to IIRemove Power/Light Poles". <br />b) Item 16 of the bid form calls for the replacement of brick pavers. Can you <br />provide specs for the type of brick pavers that are required? Or do we <br />have to match the existing brick pavers? If the intention of the plans is to <br />match the existing pavers, please be advised that based on past <br />experience some of the pavers could be discontinued, and if available the <br />color will probably not match the rest of the pavers in the driveway. <br />Owners tend to be very unreasonable when the color of their pavers don't <br />match perfectly. Please advise? <br />Response: A standard apron is shown on the plans with a set <br />distance from the edge of the proposed road to the existing <br />driveways. Instructions are to saw cut the drives regardless of <br />material and match with the proposed pavement. Due to grade <br />deferential between the proposed road and the existing driveway, the <br />paver bricks must be removed and replaced after regrading the <br />driveway. In all cases, the existing pavers are to be salvaged for this <br />work and any excess shall become the property of the owner. <br />c) What is the estimated cost for this project? <br />Response: $1,345,000 excluding the water distribution and FPL <br />underground. <br />d) Can you provide boring logs for this project? The cut for gravity sewer at <br />some locations is 10 feet below existing grade. It will be very helpful to <br />know what the soil strata consists of. <br />Response: See attached Geotechnical Report in this addendum. <br />e) Are there any weight restrictions on the bridges? <br />Response: Yes, 2 front bridges to Collins 99 tons, no load on <br />historical bridge. <br />f) If unsuitable material is found at the bottom of the pipe trench, how deep <br />below the invert of the pipe will the contractor be required to excavate and <br />remove the unsuitable material? Will the additional suitable fill require for <br />backfilling above and below the pipe be paid under Item 14, Select Fill <br />Materials? <br />Response: Yes, however, the quantities removed shall be in <br />accordance with Miami-Dade WASD standards and specifications for <br />sanitary sewer; FDOT for drainage collection system; City of North <br />Miami for the water distribution system. <br />g) Item 12 of the bid form calls for FC 12.7 asphalt instead of SP-9.5 as <br />shown on Sheet C-18 and 19. Which is correct? <br />Response: Fe 12.7. <br />h) What type of asphalt is required for Item No. 17? <br />Response: SP 9.5 for the Laguna only. <br /> <br />04/08 Final Version <br /> <br />00900-2 <br /> <br />05-4893 <br />