<br /> STANDARD FORM 330
<br />
<br />E. RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT
<br />(Complete one Section E for each key person.)
<br />12. NAME Osmany Alfonso, P.E. 13. ROLE IN THIS CONTRACT Senior Structural Project Engineer 14. YEARS EXPERIENCE
<br />a. TOTAL 22 b. WITH CURRENT FIRM 5
<br />15. FIRM NAME AND LOCATION (City and State) A&P Consulting Transportation Engineers, Corp., Doral, Florida
<br />
<br />16. EDUCATION (DEGREE AND SPECIALIZATION)
<br />• Bachelor of Science – Civil Engineering December
<br />1995, Florida International University, Miami, Florida
<br />17. CURRENT PROFESSIONAL REGISTRATION (STATE AND DISCIPLINE)
<br />• Florida Professional Engineer No. 61601
<br />18. OTHER PROFESSIONAL QUALIFICATIONS (Publications, Organizations, Training, Awards, etc.)
<br />
<br />19. RELEVANT PROJECTS
<br />a.
<br />(1) TITLE AND LOCATION (City and State) Districtwide Pedestrian and Bicycle Support, FDOT, District 6
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES On-Going CONSTRUCTION (If applicable) N/A
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Ms. Diaz provided services as a Senior Traffic Engineering Analyst and leads the performance of traffic engineering studies to investigate the
<br />need for pedestrian and bicycle safety improvements districtwide..
<br />b.
<br />(1) TITLE AND LOCATION (City and State) Pedestrian Safety and Mobility Evaluation along SR 90/SW 8th
<br />Street/SW 7th Street from SR 9/SW 27th Avenue to SR 5/Brickell
<br />Avenue, Miami FL
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES On-Going CONSTRUCTION (If applicable) N/A
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />The scope of services for this study included extensive pedestrian counts and documentation of existing conditions including land uses, transit
<br />ridership and pedestrian and bicycle crash data. The 3-mile study segment was divided into homogeneous sections based on land use and
<br />pedestrian activity for analysis. The study also included plotting pedestrian and bicycle crashes to identify crash clusters and assessing the
<br />need for mid-block pedestrian crossings using the guidelines contained in the Traffic Engineering Manual (TEM). The study recommendations
<br />included overhead Rectangular Rapid Flashing Beacons (RRFBs) at several locations.
<br />c.
<br />(1) TITLE AND LOCATION (City and State) Districtwide Planning & Environmental Management Services, FDOT,
<br />District Six
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES 2012 CONSTRUCTION (If applicable)
<br />N/A
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />Task work order driven contract which includes traffic data collection, general planning, corridor/project planning, preliminary design and
<br />engineering, project development and environmental, traffic operations analysis, interchange analysis reports, systems planning, travel
<br />demand forecasting, and public involvement. Ms. Diaz served as the lead engineer for the pedestrian and bicycle safety study on SR
<br />5/Biscayne Boulevard from NE 55th Terrace to NE 77th Street
<br />d.
<br />(1) TITLE AND LOCATION (City and State) Districtwide Traffic Operations/Safety Studies Contract, FDOT, District
<br />Six
<br />(2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES 2011 CONSTRUCTION (If applicable) N/A
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />As DPM, Ms. Diaz was responsible for reviewing all types of study tasks outlined in the Scope of Services for this contract, e.g., Qualitative
<br />Assessment, Signal Warrant Analysis, Intersection Analysis, Left Turn Phase Warrant Analysis, and Speed Zone Studies. Through this contract,
<br />Ms. Diaz performed skid hazard location investigations consistent with the objective of the Highway Safety Improvement Program. Ms. Diaz
<br />investigated and reported possible slippery pavement sections in Miami Dade and Monroe Counties. Ms. Diaz was responsible for reviewing
<br />the data stored in the FDOT Skid Hazard Reporting System, identifying highway sections with a friction number in questionable or review
<br />categories, and updating the System documenting all activities, e.g., review of crash summaries, geometrics, surface condition, posted speed,
<br />recent projects, etc., related to the highway sections investigated
<br />e.
<br />(1) TITLE AND LOCATION (City and State) Districtwide Pushbutton Minor Design Contract, FDOT, District Six (2) YEAR COMPLETED
<br />PROFESSIONAL SERVICES 2006 CONSTRUCTION (If applicable) N/A
<br />(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE Check if project performed with current firm
<br />As DPM for this work order driven contract, Ms. Diaz was responsible for reviewing roadway, signing/pavement markings, signal design plans,
<br />and construction cost estimates for the implementation of traffic safety and operational improvements, e.g., school zone, audible pedestrian
<br />signal, and traffic signal installation. Ms. Diaz was responsible for the administration of two Minor Design Pushbutton Contracts & overseeing
<br />all activities related to the production of design plans at the 90% and 100% phase levels in conformance with FDOT Standards
<br />